A payment certificate that is not paid on time is one of the most common, and most damaging, problems on a South African building site. Contractors carry wages, materials and plant costs every month; a single unpaid certificate can push a sound business into distress.
The good news for contractors is that a properly issued payment certificate is a strong document in law. The good news for employers is that the contract usually gives them legitimate ways to deduct or dispute amounts, provided they follow it. This article covers both sides.
What a payment certificate is
Under the main standard-form contracts used in South Africa, the contractor does not simply invoice the employer. A certifier assesses the value of work done and issues a payment certificate:
- under the JBCC Principal Building Agreement, the principal agent issues interim and final payment certificates;
- under the NEC contracts, the project manager assesses the amount due and certifies payment;
- under FIDIC and the GCC (General Conditions of Contract for Construction Works), the engineer certifies.
Once a certificate is issued, the employer must pay the certified amount within the period the contract sets, commonly between 7 and 30 days. Subcontractors are usually paid through a parallel process under their subcontract.
Why a certificate is a strong document
South African courts have long treated a signed payment certificate as a liquid document: a written acknowledgment of a fixed sum that is due. In Smith v Mouton 1977 (3) SA 9 (W) and later cases, courts recognised that an interim certificate gives the contractor a self-standing right to payment of the certified amount.
In practice, this means a contractor can often sue on the certificate itself without first proving the value of every item of work. That makes summary judgment, or a quick application, a realistic option against an employer who simply does not pay.
There are limits. In Thomas Construction (Pty) Ltd v Grafton Furniture Manufacturers 1988 (2) SA 546 (A), the contractor’s liquidators could not enforce interim certificates after the employer had validly cancelled the contract. Interim payments are essentially advance payments towards the final contract sum. Once the contract ends, the final account between the parties usually governs.
A contractor’s options when a certificate is unpaid
Check your contract first: the remedies below depend on its wording and on following its notice procedures exactly.
- Send a formal written demand. Refer to the certificate, the due date and the contract clause. This is often enough, and it builds the record for later steps.
- Claim interest. Most standard forms provide for interest on late payment. If the contract is silent, interest at the prescribed rate under the Prescribed Rate of Interest Act 55 of 1975 runs from the date payment was due.
- Suspend the works. The JBCC and other standard forms allow a contractor to suspend work after giving notice of non-payment, and to claim the resulting time and cost. Suspending without following the contractual steps can itself be a breach, so get the notices right.
- Refer the dispute to adjudication. If the employer disputes the amount, adjudication gives a binding decision within weeks. Courts enforce these decisions promptly. See our guide to construction adjudication in South Africa.
- Issue legal proceedings. Where the certificate is not disputed, an action or application on the certificate is often the fastest route to judgment.
- Cancel the contract. Persistent non-payment may entitle the contractor to terminate. This is a serious step with significant consequences, and it should only be taken on legal advice.
Watch the clock. Ordinary contractual debts prescribe after three years under the Prescription Act 68 of 1969. A certificate left unpaid while the parties “talk it through” can become unenforceable.
What employers can, and cannot, do
Employers often have good reasons to pay less than the full certificate: defective work, delay penalties, or amounts paid to others to finish work. The question is whether the contract allows the deduction.
- Deduct only what the contract permits. Standard forms usually allow defined deductions, such as penalties for late completion or contra charges, typically with prior written notice. A deduction outside those provisions is likely a breach.
- Dispute through the contract, not by silence. If you believe the certifier got the valuation wrong, raise it formally and use the dispute resolution clause. Simply not paying exposes you to interest, suspension and costs.
- Remember the certifier’s role. The principal agent or engineer is your appointee but must certify fairly. Pressuring a certifier to hold back a certificate can strengthen the contractor’s claim.
- Pay-when-paid clauses are generally enforceable. South Africa has no statutory ban on them, because the proposed CIDB prompt payment regulations never came into force. Main contractors relying on such a clause should make sure it is clearly drafted.
Preventing payment disputes
Most payment disputes start long before the certificate. Clear contract data, a realistic payment period, defined variation procedures and a named adjudicator all reduce the room for argument. If you are about to sign a building contract or subcontract, a short contract review is far cheaper than a dispute.
How O’Reilly Law can help
We help contractors recover unpaid certificates quickly, and help employers manage deductions and disputes without breaching the contract. Speak to our litigation and dispute resolution team about demands, adjudication referrals, enforcement and summary judgment.