The financial failure of a main contractor in the middle of a project is one of the worst events an employer can face. Work stops. Subcontractors leave. Plant is removed. The cost of finishing with another contractor is almost always higher than the unpaid balance of the contract.
What the employer does in the first days determines how much of that loss it recovers. Business rescue and liquidation are different processes with different rules, and a step that is lawful in one can be unlawful in the other. This article sets out the position for each.
Before it happens: read the signs
Contractors seldom fail without warning. Common signs are slowing progress, subcontractors and suppliers complaining that they have not been paid, requests for early or direct payments, plant leaving the site and key staff resigning. An employer who sees them should act at once.
- Find the guarantees. Check the expiry dates and the events that allow a call.
- Make sure payment certificates reflect work actually done. Overpayment is unlikely to be recovered.
- Check who owns materials that have been paid for, particularly materials stored off site.
- Confirm that the contract works insurance is in force and who holds the policy.
- Read the termination clause and its notice requirements.
Business rescue
Business rescue under Chapter 6 of the Companies Act 71 of 2008 begins when the board files a resolution with the Companies and Intellectual Property Commission or when a court makes an order. A business rescue practitioner takes control of the company and tries to develop a plan to rescue it or to achieve a better return for creditors than liquidation would.
What the employer cannot do
- Start or continue legal proceedings. Section 133 places a moratorium on legal proceedings and enforcement action against the company without the practitioner’s written consent or the leave of the court. Adjudications and arbitrations are affected.
- Take property in the company’s possession. Section 134 prevents any person from exercising rights over property lawfully in the company’s possession without the practitioner’s written consent, whoever owns it.
- Insist on performance. Under section 136(2) the practitioner may suspend the company’s obligations under a contract for the duration of the rescue, or apply to court to cancel them. The employer is then left with a claim for damages.
What the employer can do
- Terminate, if the contract allows it. In Cloete Murray NO v FirstRand Bank Ltd t/a Wesbank 2015 (3) SA 438 (SCA), the Supreme Court of Appeal held that cancelling an agreement is not enforcement action for purposes of the moratorium. An employer may therefore exercise a contractual right to terminate. Whether it has one depends on the contract. Some forms and many amended contracts list business rescue or insolvency as a ground. Others require an actual default, such as failing to proceed with the works, and a notice procedure that must be followed exactly.
- Withhold payment for work not done. If the contractor’s obligation to build is suspended, the employer is not obliged to pay for work that has not been performed.
- Call on guarantees, as discussed below.
- Negotiate. The practitioner needs to know whether the project can be completed profitably. Outcomes that are often agreed include completion under the practitioner’s supervision with subcontractors paid directly, a transfer of the contract to another contractor, or an agreed termination with an orderly handover.
An employer with a claim against the contractor is a creditor and may vote on the business rescue plan. Quantify the claim and lodge it with the practitioner.
Liquidation
Liquidation begins with a court order or a resolution, and a liquidator is appointed to realise the company’s assets for its creditors.
- The contract does not end automatically. The liquidator chooses whether to complete the contract or to abandon it, and must decide within a reasonable time. Liquidators seldom complete construction contracts.
- The employer cannot compel performance. If the liquidator abandons the contract, the employer has a claim for damages, which ranks as a concurrent claim and is rarely paid in full.
- Termination clauses. A clause that entitles the employer to terminate on the contractor’s liquidation is generally enforceable. Use it, following the notice requirements, so that the employer’s right to take over the site is clear.
- Legal proceedings against the company are stayed once winding-up starts.
- Retention and unpaid certificates. Money the employer still holds can ordinarily be applied against the cost of completing the works and remedying defects, in the manner the contract provides. Expect the liquidator to test the calculation.
The site
An abandoned site is exposed to theft, vandalism, weather and injury claims. Securing it is urgent, but it must be done lawfully.
- Possession. If the contractor is still in possession, the employer may not simply lock it out. Possession should be taken after a valid termination, or by agreement with the practitioner or liquidator.
- Record everything. Arrange a joint inspection where possible. Have the quantity surveyor value the work done and list the defects. Photograph the site. Make an inventory of materials and plant. Collect the drawings, test certificates, warranties and the health and safety file.
- Insurance. If the contractor arranged the works insurance, it may lapse. The employer should arrange its own cover from the date of termination.
- Health and safety. The client’s duties under the Construction Regulations, 2014 continue. A new principal contractor must be appointed in writing before work resumes.
Materials, plant and subcontractors
Materials. Who owns materials on site depends on the contract and on the supplier’s terms. Many construction contracts provide that ownership passes to the employer once the materials have been paid for in a certificate. A supplier who has not been paid by the contractor may have reserved ownership. Once materials are built into the works they become part of the land and belong to the landowner. Materials that have not yet been built in are the usual subject of competing claims. Obtain the written agreement of the practitioner or liquidator before using them.
Plant. The contractor’s own plant is an asset of its estate. A clause that allows the employer to use the contractor’s plant to complete the works may not bind a liquidator, and in business rescue its use needs the practitioner’s consent. Hired plant belongs to the hire company, which will want it back.
Subcontractors. Unless there are direct agreements, the employer has no contract with the subcontractors and owes them nothing. They are creditors of the contractor. Paying them directly what the contractor owes them is risky. After liquidation begins, such a payment may not discharge the employer’s own debt to the insolvent estate, and the employer could pay twice. The better course is to contract afresh with the key subcontractors for the remaining work, and to leave their historical claims to the insolvency process.
Guarantees: the real protection
A claim against an insolvent contractor is worth little. The guarantees are worth their face value.
- An on-demand performance guarantee is independent of the construction contract. The contractor’s business rescue or liquidation does not prevent a call, and many guarantees list liquidation as an event that entitles the employer to demand payment.
- The demand must comply strictly with the guarantee and must be made before it expires. Check the expiry date first.
- Advance payment guarantees, retention guarantees and parent company guarantees should each be reviewed and, where the conditions are met, called.
- Money recovered under a guarantee must be accounted for against the employer’s actual loss.
Completing the works
- Define the remaining scope accurately, including the remedial work.
- Expect a replacement contractor to exclude responsibility for work done by its predecessor, or to charge for accepting it.
- Keep detailed records of the cost to complete. They are the foundation of the employer’s claim against the insolvent estate and of its accounting for guarantee proceeds.
- Public sector employers must also satisfy their procurement rules when appointing a replacement.
A checklist for the first two weeks
- Confirm the contractor’s status: business rescue or liquidation, and the date on which it began.
- Identify the practitioner or liquidator and open communication in writing.
- Locate every guarantee and diarise its expiry.
- Stop payments that are not clearly due.
- Read the termination clause and decide, with advice, whether and how to terminate.
- Secure the site lawfully and arrange insurance.
- Carry out an inspection, valuation and inventory.
- Do not use materials or plant, or pay subcontractors directly, without agreement or advice.
- Prepare and deliver a compliant demand under the guarantees where the conditions are met.
- Quantify and lodge your claim.
- Plan the appointment of a replacement contractor.
How O’Reilly Law can help
O’Reilly Law advises employers, developers, contractors and subcontractors when a party to a construction project becomes insolvent. We advise on termination, deal with business rescue practitioners and liquidators, prepare demands under guarantees, and draft the agreements needed to complete the works. Read more about our construction and engineering work.
Question? Contact us for practical advice.
Related reading: On-demand performance guarantees · Buying a business in business rescue
This article is general information and not legal advice. Last reviewed November 2026.