Almost every construction contract requires the contractor to provide a guarantee from a bank or an insurer. While the project runs smoothly, nobody looks at it. When the relationship breaks down, it becomes the most valuable document on the project.
Employers want to know when they may call on the guarantee. Contractors want to know whether a call can be stopped. South African courts have given a consistent answer: an on-demand guarantee stands apart from the construction contract, and the grounds for preventing payment are narrow. This article explains the principles and what each side should do about them.
Two kinds of guarantee
A conditional guarantee operates like a suretyship. The guarantor is liable only if the contractor is shown to be in default, and it can raise the defences that the contractor has against the employer.
An on-demand guarantee is an independent undertaking by the guarantor to pay when it receives a demand that complies with the terms of the guarantee. The guarantor is not concerned with who is right in the underlying dispute.
Which kind you have depends on the wording, not the heading. Phrases such as payment on first written demand, and undertakings to pay regardless of any dispute between employer and contractor, indicate an on-demand guarantee. The guarantee forms commonly used with the standard construction contracts in South Africa are of this kind, with payment triggered by specified events.
The autonomy principle
The courts treat an on-demand guarantee in the same way as a letter of credit. The principle was stated for letters of credit in Loomcraft Fabrics CC v Nedbank Ltd 1996 (1) SA 812 (A) and applied to construction guarantees by the Supreme Court of Appeal in Lombard Insurance Co Ltd v Landmark Holdings (Pty) Ltd 2010 (2) SA 86 (SCA). In Coface South Africa Insurance Co Ltd v East London Own Haven 2014 (2) SA 382 (SCA) the court confirmed that a dispute about whether the employer validly cancelled the building contract does not release the guarantor.
The commercial logic is to pay now and argue later. The guarantee gives the employer cash when the events it describes occur. If it turns out that the employer was not entitled to the money, the contractor’s remedy is a claim against the employer under the construction contract.
What the employer must get right
The autonomy of the guarantee cuts both ways. The guarantor must pay on a compliant demand, and may refuse a demand that does not comply. Compliance is judged strictly against the wording of the guarantee.
- The right party. The demand must come from the beneficiary named in the guarantee and be signed by someone with authority. If the employer’s rights have been ceded to its lenders, establish who is entitled to call.
- The right address and form. Send the demand to the address and in the manner the guarantee prescribes, with the original guarantee if it must be surrendered.
- The right content. If the guarantee requires a statement that the contract has been cancelled because of the contractor’s default, or a copy of a notice or certificate, the demand must contain exactly that.
- The right sequence. Some guarantees require prior notice to the contractor, or a waiting period, before a demand is made.
- The right amount. A guarantee may reduce on practical completion or other milestones. Do not demand more than the amount then available.
- Before expiry. A guarantee expires on a fixed date or on a defined event. A demand received a day late is worthless.
Employers lose guarantees through administration, not law. Diarise expiry dates, ask for an extension well in advance where the project is running late, and have the demand prepared by someone who has the guarantee open in front of them.
When can a contractor stop a call?
Fraud
The established exception is fraud by the beneficiary. A contractor must show that the employer made the demand knowing that it was not entitled to do so. A genuine dispute about who breached the contract is not fraud, and nor is a demand based on an honest but mistaken view. The Supreme Court of Appeal emphasised how narrow the exception is in Guardrisk Insurance Co Ltd v Kentz (Pty) Ltd [2013] ZASCA 182. Fraud must be clearly established, which is difficult to do in urgent proceedings.
A non-compliant demand
If the demand does not meet the requirements of the guarantee, the guarantor is not obliged to pay. A contractor who learns of a call should read the demand against the guarantee immediately and point out any defect to the guarantor in writing.
A restriction in the construction contract
The construction contract may itself limit the circumstances in which the employer may call on the guarantee. The Supreme Court of Appeal has accepted in principle that a contractor may hold the employer to such a restriction. In the leading case, decided in 2020 and involving a national roads project, the court found that the contract contained no restriction of that kind and refused to interdict the call. The lesson for contractors is that this protection has to be written into the contract in clear terms. It will not be implied from the general scheme of the contract.
What does not work
An argument that the employer cancelled the contract unlawfully, that the contractor has counterclaims, or that the dispute has been referred to adjudication or arbitration will not ordinarily stop payment under an on-demand guarantee.
After the call
A guarantee is security, not a windfall. The employer must account for what it received. If its proven loss is less than the amount paid, the difference is owed to the contractor, and the final account or the dispute resolution process under the contract will determine it.
For the contractor the immediate consequences are severe. The guarantor will turn to the contractor under its indemnity or facility agreement, and to any directors or group companies that stood surety. Insurers and banks will reassess the contractor’s facilities for other projects. This is why the time to deal with guarantee risk is when the contract is negotiated.
Negotiating the guarantee
Contractors should ask for:
- a clause in the construction contract that limits calls to defined events, such as a certified or adjudicated amount remaining unpaid, or cancellation following the contractual notice procedure;
- written notice of an intended call, with a short period to remedy;
- a guarantee that reduces as the works progress and expires on a fixed calendar date; and
- an obligation on the employer to return the guarantee promptly when it expires.
Employers should check:
- that the guarantor is a registered bank or a licensed insurer of substance;
- that the guarantee is on demand and not conditional on proof of default;
- that it covers the contractor’s insolvency as well as breach;
- that it runs until the defects obligations have been met, or is replaced by a retention; and
- that the contract obliges the contractor to extend or replace the guarantee before it expires, failing which the employer may call on it.
Other guarantees on a project
- Advance payment guarantees secure the repayment of money paid before work is done.
- Retention guarantees replace cash retention.
- Payment guarantees are given on behalf of the employer to secure payment to the contractor, often in exchange for the contractor’s waiver of its builder’s lien.
- Parent company guarantees are usually conditional and depend on the contractor’s liability being established.
The same analysis applies to each. Read the wording, identify whether the undertaking is independent or conditional, and note the expiry.
A checklist
- Establish whether the guarantee is on demand or conditional.
- Record the expiry date or event, and review it monthly.
- Keep the original guarantee in a safe place and know who may sign a demand.
- Before calling, follow every step the guarantee and the contract require.
- Draft the demand in the words of the guarantee and attach what it requires.
- Deliver the demand in the prescribed manner and keep proof of delivery.
- If you are the contractor, check any demand for defects immediately.
- Consider an interdict only where there is clear evidence of fraud or of a breach of an express restriction on calling.
- After a call, account for the proceeds through the final account.
- Negotiate call restrictions and reduction dates before signing the contract, not afterwards.
How O’Reilly Law can help
O’Reilly Law advises employers, contractors and subcontractors on construction contracts and the security given under them. We review guarantee wording before contracts are signed, prepare and respond to demands, and act in urgent applications, adjudications and arbitrations arising from calls on guarantees. Read more about our construction and engineering work.
Question? Contact us for practical advice.
Related reading: Suretyships and personal liability · Dispute resolution clauses in commercial contracts
This article is general information and not legal advice. Last reviewed November 2026.