Defects after completion: how long contractors, developers and professionals stay liable

Practical completion is not the end of a contractor’s liability. Several clocks start running at or around that date: the contractual defects period, a longer period for latent defects, statutory warranties where the building is a home, and prescription. They run for different lengths of time and from different starting points.

Owners often believe that they have longer to claim than they do. Contractors and consultants often believe that their exposure has ended when it has not. This article sets out how the periods work and how they interact.

Patent and latent defects

A patent defect is one that a reasonable inspection would reveal. A latent defect is one that would not be found on such an inspection, such as inadequate foundations, missing waterproofing behind finishes or under-strength concrete. Contracts and the law treat the two differently, because an owner cannot be expected to complain about what it cannot see.

Contractual periods in the standard forms

The standard construction contracts used in South Africa each provide for a period after completion in which the contractor must return to fix defects, and most deal separately with latent defects. In outline:

  • JBCC. After practical completion there is a defects liability period, normally 90 days, in which listed defects must be made good before final completion is certified. A latent defects liability period then runs for five years from final completion.
  • NEC. The contract data sets a defects date, often 52 weeks after completion. The contractor must correct defects notified before that date. Liability for defects that appear later is governed by the general law and by any limitation of liability the parties have agreed.
  • FIDIC. A defects notification period, often one year, follows taking-over. The engineer then issues the performance certificate. Liability for hidden defects after that depends on the governing law and the particular conditions.
  • GCC. A defects liability period follows completion, and the contract provides separately for latent defects for a longer period.

These are the default positions. The periods are frequently changed in the contract data or the special conditions, and editions differ. Read the signed contract.

Prescription: the clock behind every clock

Whatever the contract says, a claim must also be brought before it prescribes. Under the Prescription Act 68 of 1969 an ordinary contractual claim prescribes three years after the debt becomes due. Under section 12(3), a debt is not regarded as due until the creditor knows the identity of the debtor and the facts from which the debt arises, or could have acquired that knowledge by exercising reasonable care.

Three consequences follow.

  • Time generally runs from discovery, not from completion. For a hidden defect, the three years ordinarily start when the owner knew, or should reasonably have known, the facts giving rise to the claim. An owner who ignores obvious warning signs is treated as knowing what an inspection would have revealed.
  • A contractual period does not extend prescription. If a defect is discovered in the first year after completion, the owner cannot wait until the end of a five-year latent defects period to sue. The claim will have prescribed three years after discovery.
  • A contractual period can end liability earlier. Where the contract validly limits the contractor’s liability to defects that appear within a stated period, a defect that emerges later may not be claimable at all, even though prescription has not started to run.

Stopping the clock

Prescription is interrupted by the service of a summons or, where the contract provides for arbitration, by the formal commencement of the claim. It is also interrupted by an acknowledgment of liability by the debtor, which may be express or implied. A contractor’s written undertaking to repair a defect can amount to such an acknowledgment. Letters of demand, meetings and negotiations do not stop prescription on their own.

A 2026 judgment on home builders’ warranties

In July 2026 the Supreme Court of Appeal considered when prescription begins for a claim based on a home builder’s statutory warranty to repair major structural defects. The court held that prescription does not begin merely because the homeowner has become aware of the defects. A claim for breach of the warranty to repair becomes due once the owner knows that major structural defects exist, that they result from non-compliance with the technical requirements of the National Home Builders Registration Council, and that the builder has failed or refused to repair them within a reasonable time after being notified.

The judgment turns on the particular warranty, which obliges the builder to repair. It shows that the starting point for prescription depends on how the claim is framed, and it should not be read as a general extension of time for defects claims.

Homes: statutory warranties

The Housing Consumers Protection Measures Act 95 of 1998 protects people who have homes built for them. Under section 13, a home builder is deemed to warrant that the home is fit for habitation and built in a workmanlike manner, in accordance with the Council’s technical requirements and the agreed plans. The builder must rectify, at its own cost:

  • major structural defects notified within five years of occupation;
  • roof leaks notified within twelve months of occupation; and
  • other departures from the plans and specifications notified within three months of occupation.

These warranties apply whether or not the building contract mentions them. Where a builder fails to rectify a major structural defect in an enrolled home, the Council’s warranty fund may assist, subject to its conditions.

The Housing Consumer Protection Act 25 of 2024 has been signed and will replace the 1998 Act when it is brought into force. Builders and developers should check the position when planning new projects.

Where a developer sells a new home to a buyer who is a consumer under the Consumer Protection Act 68 of 2008, that Act’s implied warranty of quality may also apply, with remedies available for six months after delivery.

Developers and later owners

The first buyer has a contract with the developer and can rely on the law of sale. A seller is liable for latent defects unless the sale validly excludes that liability, and an exclusion does not protect a seller who knew of the defect and concealed it. A developer who also built the property is in a weaker position than an ordinary seller when it comes to the consequences of defective work.

A later buyer has no contract with the builder or the professional team. A claim in delict for the cost of repairing a defective building is difficult. In Trustees, Two Oceans Aquarium Trust v Kantey & Templer (Pty) Ltd 2006 (3) SA 138 (SCA), the Supreme Court of Appeal declined to recognise a delictual claim against structural engineers for negligent design, where the owner could have protected itself by contract.

The practical answer is contractual. A buyer of a recently completed building should ask the seller to cede its rights against the contractor and the consultants, and the benefit of any guarantees and manufacturers’ warranties. A funder or an anchor tenant can ask for direct warranties from the contractor and the design team when the building is constructed.

Architects, engineers and other professionals

Professionals owe their client a contractual duty to exercise reasonable skill and care. Their standard appointments commonly limit the amount of their liability and the period within which a claim may be made. An employer should read those limits before signing and negotiate them where the project justifies it.

Professional indemnity insurance normally responds to claims made while the policy is in force, not to work done while it was in force. An appointment should therefore oblige the consultant to maintain cover for a period after completion, and to provide proof each year.

Practical steps

For owners and employers:

  • inspect thoroughly before each contractual period expires, with professional help for structure, roofs and waterproofing;
  • notify defects in writing, in the manner the contract requires, and keep proof;
  • hold the retention or the guarantee until final completion is properly achieved;
  • record the date on which each defect was discovered, and diarise three years from that date; and
  • if repairs are promised but not carried out, start formal proceedings in good time.

For contractors and developers:

  • make sure subcontracts and supply agreements carry warranties that last at least as long as your own liability;
  • keep the project records, test results and as-built drawings for the whole liability period;
  • respond to defect notices promptly, and be clear about whether you accept responsibility; and
  • keep your insurance in place after completion.

A checklist

  1. Identify the defects liability period and the latent defects period in the signed contract.
  2. Check for any clause that limits liability by amount or by time.
  3. Establish whether the home builder legislation applies.
  4. Record when each defect was, or should have been, discovered.
  5. Calculate prescription from that date, not from completion.
  6. Notify defects formally and in time.
  7. Do not rely on correspondence to stop prescription.
  8. Check the consultants’ liability limits and insurance.
  9. On a purchase, obtain a cession of warranties and guarantees.

How O’Reilly Law can help

O’Reilly Law advises employers, developers, contractors and consultants on construction contracts and the disputes that arise from them. We advise on defects claims and liability periods, draft warranty and cession arrangements for purchasers and funders, and act in adjudications, arbitrations and court proceedings. Read more about our construction and engineering work.

Question? Contact us for practical advice.

Related reading: Prescription of debts in South Africa · On-demand performance guarantees

This article is general information and not legal advice. Last reviewed November 2026.