A solar plant is built in months and operated for decades. The construction contract gets most of the attention, but it is the operation and maintenance (O&M) agreement that decides whether the plant produces what the financial model assumed, year after year.
This matters to every owner of a commercial rooftop system, a ground-mounted plant or a project that wheels power to customers. It matters to lenders and offtakers too, because their returns depend on the plant running. This article looks at the clauses that carry the most weight: scope, the availability guarantee, the performance ratio, response times and the remedies when the contractor falls short.
What an O&M agreement covers
A typical scope includes:
- Preventive maintenance: scheduled inspections, testing, cleaning and servicing in line with the manufacturers’ manuals.
- Corrective maintenance: finding and fixing faults when they occur.
- Monitoring and reporting: remote monitoring, alarms, and monthly and annual performance reports.
- Site upkeep: module cleaning, vegetation control, drainage, fencing and, on larger sites, security.
- Spare parts: holding and replenishing an agreed stock.
- Warranty administration: lodging and pursuing claims against equipment manufacturers and the construction contractor.
Asset management is a different service. It covers invoicing the offtaker, managing insurance, reporting to lenders and regulators, and running the project company. Some contractors offer both. If so, the two scopes and fees should still be set out separately, so that one can be ended without the other.
Scope gaps: where many disputes start
The fixed annual fee covers only what the scope schedule says it covers. Disputes often begin with work that each party assumed the other was paying for. Before signing, test the schedule against these questions:
- Does the fee include the labour for corrective maintenance, or only a set number of call-outs?
- Who pays for replacement parts once the manufacturer’s warranty has expired, particularly inverters?
- How many module cleaning cycles are included, and who decides when extra cleaning is worthwhile?
- Who carries the cost of theft, vandalism and storm damage, and who manages the insurance claim?
- Who owns the spare parts, and must the contractor restore the stock to the agreed level at its own cost when it uses them?
- Is work required by a change in law or a new grid requirement an extra?
Out-of-scope work should be done at pre-agreed rates, with a written quote and the owner’s approval required above a stated amount.
The availability guarantee
Availability measures how much of the time the plant was able to generate. It is the guarantee O&M contractors accept most readily, because it reflects what they control: keeping the equipment running and repairing it quickly.
The guaranteed percentage is only the headline. The definition is what counts.
- Time-based or energy-based. A time-based formula counts every hour of downtime equally. An energy-based formula weights downtime by the energy that was lost, so an outage at midday in summer counts for more than one at dusk in winter. The second tracks revenue more closely.
- Level of measurement. Measuring at inverter or string level captures partial outages. Measuring only at the plant’s point of connection can hide them.
- Which hours count. Availability should be measured only when there is enough sunlight to generate, using an agreed irradiance threshold.
- Exclusions. Contractors reasonably ask to exclude downtime caused by grid outages, curtailment instructed by the network operator, force majeure, the owner’s own acts and an agreed allowance for planned maintenance. Each exclusion should be defined narrowly, and the contractor should have to show that it applies.
- Measurement period. Annual measurement smooths out bad months. Owners who depend on steady cash flow may want a monthly or quarterly test as well.
Planned maintenance that requires a shutdown should be scheduled outside peak generating hours wherever possible, and the agreement should say so.
Performance ratio: a harder guarantee
The performance ratio compares the energy the plant delivered with the energy it should have delivered given the sunlight that reached the modules. It tests the quality of the whole plant, not only its uptime.
Because the ratio depends heavily on design, equipment quality and module degradation, an O&M contractor that did not build the plant may be reluctant to guarantee it. Where a performance ratio guarantee is given, check that the agreement deals with:
- calibrated irradiance and temperature sensors, and who maintains them;
- temperature correction and an agreed annual degradation allowance;
- the treatment of soiling, shading and grid events; and
- how the guarantee fits with the construction contractor’s performance guarantee during the defects liability period, so that the two contractors cannot each point at the other.
Response and repair times
An availability guarantee measured once a year will not, on its own, make a contractor hurry on a Tuesday afternoon. Service levels fill that gap. Faults are usually graded by severity, with a time to acknowledge the alarm, a time to attend site and a time to restore generation for each grade.
The owner should have continuous access to the monitoring platform, not only to the contractor’s monthly report. Independent visibility of alarms and output is the simplest way to verify what the report says.
Remedies when the contractor underperforms
Liquidated damages. The usual remedy for missing the availability guarantee is a pre-agreed amount designed to compensate for lost revenue. Three points need care. First, the formula should reflect the revenue actually lost, including under the plant’s power purchase agreement. Second, contractors generally insist on a cap, commonly linked to the annual fee. A low cap can leave the guarantee with little practical value on a large plant, so the cap is as important as the percentage. Third, the Conventional Penalties Act 15 of 1962 applies. A party cannot recover both the penalty and damages for the same breach, and can claim damages instead of the penalty only if the contract expressly says so. A court may also reduce a penalty that is out of proportion to the prejudice suffered.
Bonus. Some agreements pay the contractor a bonus for exceeding the guarantee. A modest bonus can align interests, provided it is funded by real additional revenue.
Termination for underperformance. The owner should be able to terminate if availability falls below a lower floor, if the damages cap is reached, or for repeated service level failures. Lenders will usually expect these rights and may ask for their own right to step in under a direct agreement.
Termination for convenience. Long O&M terms give price certainty but can lock an owner into a poor relationship. A right to terminate on notice after an initial period, with a defined and limited payment, preserves flexibility.
Warranties and the construction interface
For the first years of operation, three sets of promises overlap: the construction contractor’s defects liability, the manufacturers’ product and performance warranties, and the O&M contractor’s obligations. The O&M agreement should require the contractor to:
- maintain the plant in the manner the manufacturers’ warranties require, and carry the consequences if its conduct voids a warranty;
- identify defects, gather evidence and manage claims on the owner’s behalf; and
- record the condition of the plant at handover, so that later arguments about pre-existing defects can be resolved on the facts.
Where the O&M contractor is related to the construction contractor, the owner should keep the right to pursue warranty claims itself, because the contractor has a conflict of interest.
Safety and statutory compliance
The plant is a workplace. Under section 37 of the Occupational Health and Safety Act 85 of 1993 an owner can be held responsible for the conduct of its contractors unless the parties have agreed in writing on the arrangements and procedures to ensure the contractor’s compliance with the Act. A section 37(2) agreement should be signed together with the O&M contract, and the contractor’s safety documentation and competencies should be checked.
Work on the electrical installation must be carried out or supervised by suitably registered persons. A grid-connected plant must also keep meeting the technical requirements of its connection agreement and the applicable grid code. The agreement should make the contractor responsible for operating within those requirements and for supporting any compliance testing the network operator calls for.
Price, term and handover
Fees are usually fixed per year by reference to the size of the plant, and escalate annually. Link escalation to a published index and be clear about the base date. Check what happens to the fee if part of the plant is out of service for a long period for reasons outside the contractor’s control.
The end of the contract deserves as much thought as the start. On expiry or termination the contractor should hand over all operating data, manuals, as-built drawings, spare parts, keys, passwords and access rights to monitoring and control systems, and should cooperate with an incoming contractor for a defined period. The agreement should state that the plant’s operating data belongs to the owner.
A checklist for owners
- Read the scope schedule line by line and list what is excluded from the fixed fee.
- Settle who pays for parts after warranties expire.
- Choose an energy-based availability formula where possible, and measure below plant level.
- Limit the exclusions from availability and put the burden of proof on the contractor.
- If a performance ratio guarantee is offered, check the sensors, corrections and degradation allowance.
- Set response and repair times by fault severity.
- Test the liquidated damages formula against a worked example, and look hard at the cap.
- Include termination rights for persistent underperformance and for when the cap is reached.
- Protect manufacturer and construction warranties.
- Sign a health and safety agreement and confirm registrations and insurance.
- Secure ownership of data and a full handover on exit.
- Check that the agreement meets your lenders’ requirements before it is signed.
How O’Reilly Law can help
O’Reilly Law advises plant owners, developers, contractors and funders on energy project contracts, including EPC and O&M agreements, power purchase agreements and land and rooftop leases. We draft and negotiate O&M agreements, review availability and performance guarantee regimes, and act in disputes when a plant underperforms. Read more about our energy and projects work.
Question? Contact us for practical advice.
Related reading: Service level agreements in South Africa · Penalty clauses and the Conventional Penalties Act
This article is general information and not legal advice. Last reviewed November 2026.