A group arrives at the site gate. Its members say that they represent local business, demand a share of the contract or a payment, and warn that work will stop if they do not get it. Sometimes they are armed. The site manager has minutes to decide what to do.
This has become a familiar risk on South African projects. In July 2026 the Minister of Public Works and Infrastructure reported that more than 770 cases of construction-related extortion and intimidation had been reported, and 241 arrests made, since government and industry signed the Durban Declaration in November 2024. Industry estimates put the value of public projects delayed by such conduct at about R63 billion.
Contractors and employers need a legal plan before the first visit, not after it. This article sets out the criminal law, the urgent civil remedy, the relief available under the construction contract and the safety duties that apply.
What the law calls it
Demanding money or work by threat is not a negotiation. Depending on the facts, it may be:
- extortion, a common-law crime;
- intimidation under the Intimidation Act 72 of 1982;
- trespass under the Trespass Act 6 of 1959;
- malicious damage to property, assault or public violence; and
- where a group operates in an organised way, offences under the Prevention of Organised Crime Act 121 of 1998.
This is different from legitimate community participation. Many contracts, particularly in the public sector, set targets for local labour and for subcontracting to local and small businesses. Those targets are set by the employer in the tender and the contract, and they are met through an open process. No law entitles any group to a fixed percentage of a contract on demand.
The first response
- Protect people. If there is a threat of violence, stop work in the affected area and move staff to safety.
- Do not pay and do not sign. A payment or an agreement made under threat invites further demands, on this site and on the next.
- Record. Note names, vehicle registrations, what was demanded and what was threatened. Keep video and photographs.
- Report to the police and obtain a case number. Use any dedicated reporting channel that government or the industry has set up for site extortion.
- Notify the employer’s agent in writing the same day. This starts the contractual process described below.
- Notify the insurers.
Why paying is not a solution
Apart from encouraging repetition, payments create legal exposure. Section 34 of the Prevention and Combating of Corrupt Activities Act 12 of 2004 obliges a person who holds a position of authority, which includes directors and managers, to report to the police if he or she knows or ought reasonably to know or suspect that certain offences involving R100,000 or more have been committed. Extortion is one of the listed offences. Failing to report is itself an offence. A company that quietly pays and records the payment as a consultancy fee compounds the problem.
Interdicts
The civil remedy is an urgent interdict from the High Court. A typical order restrains the named respondents, and those acting with them, from entering the site, obstructing access, threatening or assaulting staff and interfering with the works, and authorises the sheriff, with the assistance of the police, to give effect to it.
- Evidence. The application is brought on affidavit. Statements from the people who were present, supported by footage and the police case number, are essential. This is why records made on the day matter.
- Respondents. Name individuals and organisations where they can be identified. Where they cannot, the court can be asked to direct how the application and the order are to be brought to the attention of those involved, for example by posting them at the site.
- Who applies. The contractor in possession of the site usually applies. An application supported by the employer, or brought jointly, carries more weight. In August 2026 a metropolitan municipality obtained a High Court interdict to protect a public transport construction project from interference of this kind.
- Enforcement. An order is only as good as its enforcement. Serve it properly, give copies to the local police station and site security, and be prepared to bring contempt proceedings if it is ignored. The order also supports the criminal case.
Relief under the construction contract
A stoppage costs time and money. Whether the contractor recovers either depends on the contract, and on giving notice in time.
Give notice at once
The standard forms bar claims that are not notified within a fixed period. The period starts when the contractor becomes aware of the event, not when the stoppage ends. Give notice on the first day and update it.
How the standard forms allocate the risk
The unamended standard forms treat civil unrest differently.
- Under the JBCC building agreement, civil commotion and riot are among the events for which the contractor is entitled to an extension of time but not to additional payment.
- Under the NEC contract, riot and civil commotion not confined to the contractor’s own employees are an employer’s risk, which makes the event a compensation event with time and money.
- Under the FIDIC forms, riot, commotion or disorder caused by persons other than the contractor’s personnel is treated as a risk that entitles the contractor to relief.
Employers frequently amend these provisions so that the contractor is deemed to have allowed for community unrest in its price. Read the special conditions before tendering, and price or qualify accordingly.
Other contractual points
- Security costs. Additional guards, escorts and fencing are expensive. A provisional sum for security and community liaison, adjustable against actual cost, is fairer to both parties than a fixed allowance.
- Suspension and termination. Check whether the contract allows suspension when the site is unsafe, and whether either party may terminate after a prolonged stoppage.
- Subcontracts. Subcontractors will claim for standing time. Make sure the subcontract passes the main contract’s risk allocation and notice requirements down the chain.
- Penalties. A contractor that has been denied an extension of time and faces delay penalties may ask for the penalty to be reduced under the Conventional Penalties Act 15 of 1962 if it is out of proportion to the employer’s prejudice.
Safety and security duties
- Health and safety. The Occupational Health and Safety Act 85 of 1993 requires an employer to provide a working environment that is safe, as far as is reasonably practicable, for its employees and for others affected by its activities. The Construction Regulations, 2014 require the client to prepare a baseline risk assessment and the principal contractor to maintain a health and safety plan. On a project in an affected area, the threat of violent disruption belongs in both. Withdrawing workers from a site that has become dangerous is the performance of a legal duty.
- Private security. Security providers and their officers must be registered under the Private Security Industry Regulation Act 56 of 2001. Check registration before appointing a provider, and agree rules on the use of force.
- Insurance. Damage caused by riot and public disorder is typically covered by the state-owned special risks insurer and not by an ordinary policy. Confirm that this cover is in place for the works, and check whether it extends to loss caused by delay. Standing time is often uninsured.
Prevention: get community participation right
A project that has an open and credible process for local participation gives opportunists less to work with, and gives the court a clear picture of who is acting lawfully.
- Establish the contract’s local labour and subcontracting targets, and plan how they will be met.
- Appoint a community liaison officer and work through a project steering committee that includes recognised community structures.
- Advertise subcontracting and employment opportunities openly, apply stated criteria and keep records of the awards.
- Communicate early, before the contractor establishes on site.
- Decline informal side arrangements, however small.
The employer’s role
An employer that leaves the contractor to deal with the problem alone will pay for it later, in claims, in delay or in the price of the next tender. Employers should allocate the risk fairly in the contract, fund reasonable security measures, support interdict applications and engage with the police at a senior level. Public sector employers have the additional weight of the commitments that government made in the Durban Declaration.
A checklist
- Assess the risk of disruption before tendering and read how the contract allocates it.
- Include security and community liaison in the price or in a provisional sum.
- Put a response procedure in the site safety plan and brief site management on it.
- Set up a transparent local participation process before work starts.
- When an incident occurs, protect people first.
- Do not pay and do not sign under threat.
- Record the incident and report it to the police.
- Give contractual notice the same day.
- Notify insurers.
- Apply for an interdict where threats continue, and enforce it.
- Keep records of the delay and cost for the claim.
How O’Reilly Law can help
O’Reilly Law acts for contractors, subcontractors and employers in construction disputes. We bring urgent interdict applications to protect sites and staff, advise on notices and claims for time and cost under the JBCC, NEC, FIDIC and GCC contracts, and advise on risk allocation before contracts are signed. Read more about our construction and engineering work.
Question? Contact us for practical advice.
Related reading: Delay claims, notices and time bars · OHS Act duties of employers and directors
This article is general information and not legal advice. Last reviewed November 2026.